What is a commercial painting scope of work?
A commercial painting scope of work is the written list of what will be painted, how each surface will be prepared, which products go on in how many coats, when the crew may work, and what is excluded. When every bidder prices the same written scope, the bids can be compared line by line. Without one, the lowest price usually means the smallest scope.
- List areas and surfaces separately, so each one can be priced, phased or cut.
- Name the preparation, the primer, the finish and the number of coats for every surface.
- Write down working hours, protection, cleanup and exclusions before bids go out.
- In an older building, say who tests the existing paint for lead before sanding or scraping.
What a painting scope of work is for
A scope of work does two jobs. Before the contract, it makes sure every painter prices the same work. After the contract, it is the document both sides point to when a question comes up about a wall, a coat or a repair.
Most disputes on commercial repaints start with something the scope never mentioned: who moves the furniture, whether the door frames are included, whether one coat was enough over the old color. Writing those answers down first costs an hour and saves the argument.
What a commercial painting scope should include
These eleven items cover most interior and exterior repaints of offices, retail centers, restaurants and multi-tenant buildings.
| Item | What to write | Why it matters |
|---|---|---|
| Areas and surfaces | Each room, floor or elevation, and which surfaces in it: walls, ceilings, doors, frames, trim, railings. | A bid for "the second floor" and a bid for "second floor walls only" are different jobs. |
| Surface preparation | Washing, scraping, sanding, caulking and priming required before paint. | Preparation is where low bids save money and where coatings fail. |
| Repairs | Drywall patches, stucco cracks, rust treatment, wood replacement, each with a quantity or an allowance. | Unpriced repairs come back as change orders. |
| Products | Primer and finish for each surface, named by manufacturer and product line, or "approved equal". | A contractor-grade paint and a premium scuff-resistant paint are priced very differently. |
| Sheen | The gloss level for each surface, such as flat ceilings, eggshell walls and semi-gloss doors and frames. | Sheen changes how a wall cleans and how much surface damage shows. |
| Number of coats | Coats of primer and finish per surface, and what happens on a color change. | "Paint to cover" and "two finish coats" are not the same promise. |
| Colors | Color names and numbers, where each goes, and who approves a sample before production. | A sample approved on the wall prevents a full repaint in the wrong color. |
| Working hours and access | Days and hours the crew may work, keys or badges, elevator and parking rules, noise limits. | Night and weekend work in an occupied building changes the labor cost. |
| Protection and cleanup | Who moves and covers furniture, how floors and fixtures are protected, and the daily cleanup standard. | Tenants judge the job by what the space looks like at 8am. |
| Exclusions | Anything not included: wallcovering removal, high lifts, moving heavy equipment, hazardous material work. | An exclusion written down is a decision. An exclusion left out is a surprise. |
| Close-out | Punch list walk, labeled touch-up paint, color schedule and warranty terms. | The next touch-up or tenant turnover depends on these records. |
How to describe the finish you expect
"A professional finish" means something different to every bidder. Two industry references make it specific. The Painting Contractors Association's Standard P1 defines a properly painted surface as one that is uniform in appearance, color, texture, hiding and sheen, and says it is examined without magnification from 39 inches (one meter) or more, under finished lighting, from a normal viewing position.
The Master Painters Institute's guide specification numbers gloss from level 1, a flat matte finish, to level 7, high gloss. Level 3 is the traditional eggshell and level 5 the traditional semi-gloss. Writing "MPI gloss level 3" in a scope means the same thing to every bidder, whatever each paint brand calls its sheens.
You do not need to quote either document in full. A sentence that says which standard governs inspection, and which sheen goes on which surface, is enough to give both sides the same yardstick.
Lead paint: which rule applies to a commercial building
Two federal rules are often confused. The EPA's Renovation, Repair and Painting rule covers housing and child-occupied facilities, such as daycares and preschools, built before 1978. The EPA's own frequent questions page says it does not apply to office buildings, stores and other commercial buildings, unless the work is in a child-occupied facility inside one.
OSHA's lead in construction standard, 29 CFR 1926.62, is different. It applies to all construction work where an employee may be exposed to lead, and it counts painting and renovation as construction work, with no limit by building type. Sanding, scraping or grinding old paint on steel, railings or older walls can fall under it.
For the scope, the practical line is short: say who is responsible for testing existing coatings before any sanding or scraping, and what happens to the price and schedule if lead is found.
A sample scope line
This is the level of detail that lets bids be compared. One line per area, with the preparation, system and schedule in it:
- Corridor walls, floors 2 to 4: patch dents and anchor holes, sand smooth, spot prime repairs, then two finish coats of low-VOC acrylic in an eggshell sheen (MPI gloss level 3). Color to match existing. Work Monday to Thursday, 6pm to 6am.
- Hollow metal door frames, floors 2 to 4: clean, scuff sand, spot prime bare metal, then two coats of semi-gloss enamel. Doors excluded.
- Exclusions: wallcovering removal, ceilings, moving of file storage and copiers.
Three lines like these tell a bidder more than a page of general language, and they let you drop or phase one line without asking for a new bid.
How to compare painting bids against the scope
- Send the same written scope and the same drawings or room list to every bidder.
- Walk the property with each bidder, or hold one walkthrough for all of them, so nobody prices from photos.
- Ask for a line-item price that follows the scope, not one lump sum.
- Check that each bid names its products and number of coats. Where a bid is silent, ask before you compare.
- Read the exclusions first. Most price gaps are explained there.
- Confirm the schedule: number of shifts, crew size and the date the space is handed back.
- Ask for the certificate of insurance and vendor paperwork before award, not after.
How Carolina Sky Painting scopes a job in Charlotte
Carolina Sky Painting is a commercial painting contractor in Charlotte, NC. We scope from a site walkthrough, measure the surfaces, note repairs and access, and confirm working hours. The proposal that follows lists every area and coat as its own line with the products named, and it goes out within 48 hours of the walkthrough.
If you already have a written scope or a specification, we price to it. If you do not, the walkthrough produces one. See how this works for office painting in Charlotte, or start with our commercial painting in Charlotte overview.
Sources
- EPA: Lead Renovation, Repair and Painting Program
- OSHA: 29 CFR 1926.62, Lead in construction
- EPA: Frequent questions about renovations covered by the RRP rule
- Painting Contractors Association: Standard P1, definition of a properly painted surface (2023)
- Master Painters Institute: Guide Specification 09 91 23, gloss levels (2022)
This guide is general information for planning a painting project. It is not legal or safety advice. Confirm lead and safety requirements for your building with a qualified professional.